Tag: Matuku

Matuku well completed. Kan Tan IV moves to Pateke-4H.

Posted on 31 January 2014

The Matuku-1 well in PEP 51906 offshore Taranaki has been plugged, the operator has advised.

Read the full post

Matuku-1 News Release 20 Jan 14

Posted on 20 January 2014

In PEP 51906, Matuku reaches total depth and new seismic completed. Total depth of 4846 metres was reached on Saturday, 18 January in the Matuku well in PEP 51906 offshore Taranaki. The next operation is pulling out of the hole prior to running wireline logs. The Kan Tan IV began drilling operations on Saturday, 30 November. Matuku-1 is in 130 meters of water.

Read the full post

Matuku-1 progress report 14 Jan 2014

Posted on 20 January 2014

Since the weekly progress report was issued yesterday, the Matuku-1 well in PEP 51906 offshore Taranaki has drilled into the Kapuni Group Farewell F Sands at 3935 metres. The F sands were found to be porous, but there were no significant gas or oil shows.

Read the full post

Matuku-1 update 16 Jan 14

Posted on 20 January 2014

New Zealand Oil & Gas believes its share price has been affected by the previously released news that the primary target zone in the Matuku well in PEP 51906 offshore Taranaki has not encountered significant oil or gas shows. The well is currently at a depth of 4307 metres and drilling ahead to a total depth of 4750 metres.

Read the full post

Matuku-1 weekly progress report January 13

Posted on 13 January 2014

The Matuku-1 well in PEP 51906 offshore Taranaki has been drilled to 3913 meters as of 6.00AM Sunday, 12 January 2014. A 9 5/8 inch casing string has been set to 3409 meters.

Read the full post

Matuku-1 weekly progress report January 7

Posted on 7 January 2014

As at 6:00AM Monday, 6 January, the Matuku-1 well in PEP 51906 offshore Taranaki had been drilled to 3417 metres. 9 5/8” casing has been run to 3409 metres and cemented. The current operation is running in 8 ½” drilling assembly to commence drilling the next section to a planned total depth of 4754m.

Read the full post

Matuku-1 weekly progress report December 30

Posted on 30 December 2013

As at 6.00AM Sunday, 29 December, the Matuku-1 well in PEP 51906 offshore Taranaki had been drilled to 3167 metres after setting 13 3/8” casing at 1494 metres.

Read the full post

Matuku-1 weekly progress report December 20

Posted on 20 December 2013

As at 6.00AM Thursday, 19 December the Matuku-1 well in PEP 51906 offshore Taranaki had been drilled to 2867 metres.

Read the full post

Matuku -1 Weekly Progress Report December 17

Posted on 17 December 2013

As at 6.00AM Monday, 16 December, blowout preventers had been successfully installed and tested at the Matuku-1 well in PEP 51906 offshore Taranaki.

Read the full post

Matuku-1 weekly progress report December 10

Posted on 10 December 2013

As at 6.00AM Monday, 9 December the Matuku-1 well in PEP 51906 offshore Taranaki has been drilled to 1500 metres.

Read the full post